Getting a Deal Done - Start to Finish
|
View Printable Version
|
| ACTIVITY |
TIME FRAME |
| Project Identified |
Varies |
|
|
|
|
| Application
Submitted to IHDA |
|
|
Day 1 |
|
|
|
|
| Initial
Review and Threshold/Completeness Check |
Day 20 |
|
|
|
|
| Project
Underwriting and Feasibility Review |
|
Day 20 - 60 |
|
|
|
| Peer
Review |
|
|
|
Varies |
|
|
|
|
| Loan
Committee Review |
|
|
Varies |
|
|
|
|
| Advisory Commission (If Trust Funds are
used) |
Day 70 |
|
|
|
|
| Public
Notification/Comment Period |
|
Day 70 - 100 |
|
|
|
| Environmental Review (If Federal Funds are
used add 30 days) |
Day 70 - 100 |
|
|
|
| IHDA
Board Presentation |
|
|
1st available meeting after notification period. Not later than seven months after original
application submittal. |
| Commitment
Letter Issued |
|
|
Varies by project usually with in 30 days of Board approval. |
| Loan
Closing |
|
|
|
Varies, not earlier than 45 days after approval of commitment
letter. Not later than 7 months after
Board approval. |
| |
|
|
|
| Note: The timing
of each step may vary significantly depending on the specifics of the
transaction. |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|